Migrating to Toolsoft Video Manager: A Step-by-Step ChecklistMigrating a video library and workflows to a new platform can be one of the most impactful — and disruptive — moves your team makes. Toolsoft Video Manager (TVM) promises centralized asset management, metadata control, transcoding automation, and better delivery options, but a migration done without planning risks downtime, lost metadata, broken embeds, and frustrated users. This step-by-step checklist covers planning, pre-migration preparation, execution, validation, and post-migration follow-up so your move to Toolsoft Video Manager is smooth, auditable, and reversible if needed.


Phase 1 — Discovery & Planning

  1. Define goals and success criteria

    • Identify primary reasons for migrating (cost reduction, centralized control, faster delivery, compliance).
    • Set measurable success criteria: e.g., all assets migrated with metadata preserved, zero broken public embeds, <24 hours downtime for scheduled switchover.
  2. Inventory assets and workflows

    • Count total videos, audio-only files, subtitles, thumbnails, and related documents.
    • Log content sizes, codec/container types, resolutions, and typical bitrates.
    • Map current workflows: ingestion, transcoding, QA, metadata entry, publishing, CDN distribution, access control.
  3. Identify stakeholders and assign roles

    • Appoint a migration owner, technical lead, QA lead, content lead, and communications lead.
    • Engage security/compliance, legal, and any third-party integrators (CDN, LMS, CMS).
  4. Risk assessment & rollback plan

    • Document risks (lost metadata, failed transcoding, API incompatibilities) and mitigation strategies.
    • Create a rollback plan: maintain read-only access to the source system until post-migration verification is complete.
  5. Timeline, budget, and environment readiness

    • Estimate time per asset and total migration time; include buffer for QA and reprocessing.
    • Budget for tooling, storage, CDN egress, and engineering hours.
    • Confirm Toolsoft Video Manager account, API keys, and access credentials.

Phase 2 — Preparation

  1. Clean and normalize source data

    • Remove duplicates, outdated content, and corrupted files.
    • Standardize filenames and metadata fields where possible (title, description, tags, language codes).
    • Consolidate subtitle and caption formats (e.g., prefer VTT or SRT).
  2. Map metadata schema to TVM

    • Compare source metadata fields to Toolsoft Video Manager fields.
    • Create a field mapping document and decide on transformations (e.g., converting date formats, combining author fields).
    • Mark required vs optional fields and provide defaults for missing required values.
  3. Plan transcoding & renditions

    • Decide which renditions TVM should host (e.g., 1080p, 720p, 480p, low-res proxies).
    • Identify any legacy codecs that need re-encoding.
    • Determine thumbnail extraction rules and poster image sizes.
  4. Prepare access control and publishing targets

    • Map user/groups/permissions from the old system to TVM roles.
    • Identify publishing endpoints (websites, LMS, social, CDN).
    • Prepare OAuth/API credentials for each target.
  5. Build migration tooling & scripts

    • Choose transfer method: TVM direct ingestion API, S3-compatible transfer, or staged import via temporary storage.
    • Implement scripts for uploading files, posting metadata, and requesting renditions.
    • Add logging, retry logic, and rate-limit handling.
  6. Test environment setup

    • Create a staging TVM account or project and mirror a representative content subset.
    • Test ingest, metadata import, transcoding, and publishing.
    • Validate performance and error handling.

Phase 3 — Pilot Migration

  1. Select a pilot dataset

    • Pick a representative subset: a mix of sizes, codecs, metadata complexity, and publishing destinations.
    • Include edge cases (long files, multiple subtitle tracks, DRM) in the pilot.
  2. Execute pilot migration

    • Run your migration scripts and monitor logs closely.
    • Track API responses, failed uploads, and rendition completions.
  3. QA and verification for pilot

    • Verify file integrity and checksums.
    • Confirm metadata mapping and transformations are correct.
    • Check playback across target devices/browsers and confirm captions, thumbnails, and chapter markers.
  4. Adjust scripts and mappings

    • Resolve discovered issues, refine retry logic, and update mappings.
    • Document lessons learned and update the migration runbook.

Phase 4 — Full Migration

  1. Schedule migration windows

    • Choose off-peak hours for public-facing sites.
    • Communicate planned windows to stakeholders and users.
  2. Perform staged transfers

    • Migrate in batches (by date, channel, or content type) to minimize risk.
    • Monitor throughput and adjust parallelism to avoid API throttling or CDN overload.
  3. Run live validations per batch

    • Automated checks: file counts, checksums, rendition statuses, metadata completeness.
    • Manual spot checks: playback, captions, analytics tags, and embeds on target sites.
  4. Keep source system read-only (if possible)

    • Prevent content drift during migration by setting the source to read-only, or record deltas and plan a final sync pass.
  5. Final sync and cutover

    • Run an incremental sync for items changed during migration.
    • Switch public endpoints (CDN origin, embed scripts, or API endpoints) to Toolsoft Video Manager once verified.
    • Monitor traffic, error rates, and user reports closely during the first 72 hours.

Phase 5 — Post-Migration Validation & Optimization

  1. Comprehensive verification

    • Confirm every migrated item is present, playable, and has correct metadata.
    • Run automated reports comparing source and TVM inventories.
  2. Analytics and monitoring

    • Verify analytics tags, event tracking, and dataflow to BI tools.
    • Ensure CDN caching behavior is optimal and cost-effective.
  3. Performance tuning

    • Adjust renditions, bitrate ladders, and CDN TTLs based on early playback data.
    • Implement adaptive streaming rules or ABR profiles in TVM if supported.
  4. User training & documentation

    • Train content editors, QA, and developers on TVM workflows.
    • Provide a migration summary, known issues, and troubleshooting tips.
  5. Decommission or archive source system

    • Only after full verification and stakeholder sign-off, decommission the old system or keep it archived in read-only form per retention policy.
    • Preserve a snapshot of source metadata and a manifest of migrated items for audit purposes.

Checklist — Quick Reference

  • Goals & success criteria defined ✔
  • Full asset inventory completed ✔
  • Stakeholders identified & roles assigned ✔
  • Metadata mapping document created ✔
  • Transcoding & rendition plan decided ✔
  • Migration scripts built & tested ✔
  • Pilot migration executed & validated ✔
  • Full migration staged & monitored ✔
  • Final sync, cutover, and 72-hour monitoring ✔
  • Post-migration verification, training, and decommissioning ✔

Migration Gotchas & Tips

  • Preserve original files: store originals as immutable archives in TVM or connected object storage to allow re-transcoding.
  • Watch for metadata loss: custom fields and nested metadata often require special handling.
  • API rate limits: implement exponential backoff and batching to avoid throttling.
  • Timezones and date formats: normalize dates to ISO 8601 to avoid mismatches in scheduling or publish dates.
  • CDN cache invalidation: plan for cache purges at cutover to avoid serving stale embeds.
  • DRM and licensing: verify that keys, licenses, and playback domains are configured correctly in TVM.

This checklist should give your team a clear, practical path from planning through post-migration operations. If you want, I can convert this into a printable checklist, generate migration scripts templates (example S3-to-TVM or API-driven), or produce a pilot-test plan tailored to your current source system — tell me which source you’re migrating from (e.g., Brightcove, Kaltura, Vimeo, S3).